By AGA Group & Associates · Miami, Florida
Roll-on roll-off vs container shipping is usually presented as a freight question that gets answered after the machine is chosen. That order is backwards, and it is why so many corridor purchases end up costing more than the invoice said.
The shipping mode does not follow the purchase. It constrains it. A machine that will not fit a container and cannot be driven onto a vessel is a machine you have already decided to partially dismantle, and that decision has a price, a schedule and a risk attached to it.
Settle the mode while you are still choosing between units. The machine, the mode and the paperwork are one decision, and the wider sequence around them is in the guide to importing used port equipment.
What Each Mode Actually Is
The two modes, in one paragraph each
In roll-on roll-off the machine drives aboard under its own power, or is towed aboard, and is secured on a vehicle deck. Nothing comes apart and nothing is lifted. It suits equipment that is self-propelled, road-capable enough to move across a terminal, and within the height and weight the deck can take.
In container shipping the machine is loaded into a box, which depending on the unit means a standard container, an open top, or a flat rack where the load exceeds the dimensions of a closed box. It suits equipment that fits, equipment that does not run, and equipment where the buyer wants the protection of an enclosed unit.
Why the comparison is not price per unit
Two quotes that look comparable often describe different amounts of work. One includes a machine driven aboard intact; the other includes a mast removed, secured, shipped and reinstalled at destination by somebody who has not seen that machine before.
Freight is part of the purchase, not a line after it.
What Decides the Mode
Does the machine run and drive
This is the first filter and the least negotiable. A unit that does not move under its own power is not a roll-on roll-off candidate in the ordinary sense, whatever its category says.
A machine bought as a project, a machine with a seized transmission, a machine with no brakes: all of them are cargo rather than vehicles for the purpose of getting them aboard.
Height, width and the shape of the load
Height is what disqualifies most cargo handling equipment from a closed container. A lift truck with its mast standing is taller than the door of a standard box, which is why masts come off.
Width and overhang matter for flat rack loading and for what the machine can pass through on the terminal. Measure the machine as it will travel, not as it sits on the lot.
Weight, and where the weight sits
Total weight decides handling equipment and securing. Weight distribution decides whether a machine can be lifted at all without a spreader arrangement, and counterweighted equipment concentrates mass in a way that surprises people who quote from a category rather than from a unit.
Whether the destination can receive it
A vessel that carries roll-on roll-off cargo has to call somewhere that can discharge it. Smaller regional ports are not all equipped the same way, and a mode that works into one Caribbean port may not work into the next one down the chain.
Confirm the discharge capability at the actual destination before you price the move.
What Comes Off, and What That Costs You
Disassembly is not free and it is not neutral
Taking a mast off a lift truck, removing a boom section, or dropping a cab is work at both ends performed by two different crews on two different continents. The second crew did not do the first job and does not have the first crew’s notes.
Every joint that is opened is a joint that has to be closed correctly. Hydraulic lines opened for shipment are hydraulic lines that have to be bled, and a system that was clean in Miami can arrive with air or contamination in it.
The parts that go missing are small and important
Pins, retaining hardware, hoses, brackets and the fasteners that came out with them. They travel separately, they get separated, and the machine waits.
Small parts cause big losses. A container handler held at a yard for a set of pins is as idle as one held for an engine.
Ask who reassembles before you agree the mode
If the answer is “a local mechanic will manage it”, price the risk honestly. If the answer is that the machine ships intact because the mode allows it, the comparison against a cheaper quote has just changed.
How the Mode Changes the Paperwork
The presentation requirement does not move, but custody does
For equipment inside the definition of a self-propelled vehicle in 19 CFR 192.1, 19 CFR 192.2 requires that for units exported by vessel “the required documentation and the vehicle must be presented to Customs at least 72 hours prior to export.”
That is the same whether the machine rolls aboard or travels in a box. What changes is the practical question of who has custody of the unit when it has to be produced.
A machine that has been stuffed into a container and sealed is harder to present than one standing on a yard. Sequence the presentation before the stuffing, not after, and make sure whoever handles the box knows that.
The export filing does not change either
15 CFR 30.2 requires Electronic Export Information “regardless of value” for “used self-propelled vehicles as defined in 19 CFR 192.1,” and 15 CFR 30.4 requires the filing citation to be provided to CBP “at least 72 hours prior to export.”
A mixed load can therefore carry two regimes in the same booking: self-propelled units on one track, and towed or lifted equipment such as chassis, trailers and containers on another. The split is explained in customs documents for used machinery.
Confirm classification rather than assume it
The regulation names broad categories rather than specific machines, so whether a particular unit falls inside that definition is a question for a licensed customs broker. Plan the mode and the documentation together, with the broker in the conversation early.
Where Each Mode Usually Wins
Roll-on roll-off tends to win when
The machine runs and drives, its height makes a closed container impractical, the destination can discharge it, and the cost of disassembly and reassembly would exceed the freight difference. Large lift trucks, container handlers and terminal tractors often land here.
Container shipping tends to win when
The machine fits without significant disassembly, the unit does not run, the destination has no roll-on roll-off service, or the cargo benefits from being enclosed. Smaller lift trucks, parts, attachments and mixed loads often land here.
And sometimes the honest answer is the third one
A machine whose landed cost only works on the cheaper mode, and which does not fit that mode, is a machine that does not work for that destination. That is a purchase decision, not a freight problem, and it is better discovered while other units are still on the table.
The Mistakes That Make the Freight Expensive
Quoting the move separately, and measuring from a specification sheet
Two suppliers, two quotes, no single number. The buyer approves a price that was never the price.
Published dimensions describe a configuration. The machine on the lot may have a different mast, a different attachment, different tyres or a counterweight that was changed. Measure the unit.
Booking the vessel before the documents exist
A sailing date does not accelerate a title reissue. When the booking leads the paperwork, the booking is what gets changed, usually at the buyer’s cost.
Assuming reassembly is somebody else’s problem
It is the buyer’s problem the moment the machine lands. Decide who does it, with what documentation, before the first bolt comes out in Miami.
Frequently Asked Questions
Is roll-on roll-off cheaper than container shipping?
Not reliably, and the comparison is misleading when it is made on freight alone. Roll-on roll-off usually avoids disassembly and reassembly; container shipping sometimes offers better rates and better protection. Compare the landed cost of a working machine at destination, including the work at both ends.
Can a forklift ship inside a standard container?
It depends on the unit and on what comes off. Height is normally the constraint, which is why masts are often removed for container loading. Whether that is worth doing depends on the machine, the rate difference and who will reinstall it at the other end.
Does the shipping mode change what documents are required?
The presentation requirement in 19 CFR 192.2 and the export filing obligation in 15 CFR 30.2 attach to what the equipment is, not to how it travels. What the mode changes is the practical sequencing of custody, because a unit already sealed in a container is harder to present.
What if the machine does not run?
Then roll-on roll-off in the ordinary sense is off the table and the unit moves as cargo. That is worth establishing early, because a non-running machine changes the freight plan, the handling at both ends and often the price you should be paying.
Who decides whether the destination port can receive the machine?
The terminal and the carrier serving it. Discharge capability varies across regional ports, and a mode that works into a major gateway may not work into a smaller one. Confirm it for the actual port of discharge rather than for the country.
Should the mode be settled before choosing the machine?
Yes, or at least in parallel. The mode determines what is realistic to buy, and a machine chosen without it is a machine whose true cost is still unknown when the deposit is paid.
Roll-on roll-off vs container shipping is a purchase decision wearing a logistics costume. Decide the mode while units are still being compared, measure the actual machine rather than the specification, settle who reassembles anything that comes apart, and keep the documentation on the same schedule as the booking. The freight is only the easy part when the machine was chosen with it in mind.
The container handlers currently listed are on the container handler inventory, the yard trucks and terminal tractors on the yard truck inventory, and the refurbishment and engine overhaul work behind them is described under services. The checks that belong at the yard before anything is loaded are in the pre-shipment inspection checklist, and the evidence to gather when you are not there yourself is in buying equipment sight unseen. There is also a companion piece on the site about intermodal equipment export.
About AGA Group & Associates. AGA Group & Associates sources, refurbishes and sells used cargo transportation and cargo handling equipment — chassis, yard trucks, forklifts, trailers, trucks and containers — to shipping companies, stevedores, ports, logistics operators and trucking companies in the United States, Latin America and the Caribbean. The company was established in Miami in 1995 and handles repair and refurbishment through certified and insured facilities across the U.S., with diesel engine overhaul on CAT, Cummins, Detroit and Mack units in Miami. More on the company is on the about us page.
This article is general information about shipping modes for used cargo handling and cargo transportation equipment. It does not describe any specific unit or shipment, it is not a freight quotation, and it does not replace the judgment of a licensed customs broker, a carrier or a qualified rigger. Regulations change, and the classification of a particular machine, the dimensions it travels at and the capability of a given port all depend on facts this article cannot know. Verify the applicable requirements against the current text of the regulations cited above and with a licensed customs broker before you commit to a purchase. Import requirements, emissions homologation and duties depend on the destination country; confirm them with a customs broker there before shipment.
Talk to AGA Group
AGA Group & Associates has been sourcing, refurbishing and selling used cargo handling and cargo transportation equipment out of Miami since 1995, for buyers in the United States, Latin America and the Caribbean. Chassis, yard trucks, forklifts, trailers, trucks and containers, with repair and diesel engine overhaul through our own shop and a network of certified and insured facilities across the U.S. Tell us the duty cycle, the site and the timeline, and if nothing on the lot fits, we will say so before you book a flight to see it. Start with a quote request or reach us on the contact page.
Address
2828 Coral Way, Suite 510, Miami, FL 33145
Phone
(305) 442-0072 | Fax (305) 442-0063
Email
sales@agagroup.us
English
Español